This submission plan coordinates owners, milestone dependencies, and readiness controls for Nepricor. Teams use it to monitor timeline health, resolve blockers, and decide whether content is publish-ready for sequence assembly. Readiness is calculated from deterministic component approval status across linked dossiers, rather than manual estimates. Use the edit and content assembly actions to move directly into corrective work.

Plan ID
PLAN-034
Target Date
2025-07-07
Status
Overdue
Owner
Carlos Mendez
Created
2022-08-18
Readiness Score
20/100
Calculated from 4 approved of 20 linked content components.
Blockers
7 components are missing approval snapshots.
6 components still have unresolved review comments.
Milestone Dependency Strip
Authority acknowledgement expected
Quality review
Regulatory review
Protocol finalization
QC check
Module 5 compilation
Publishing start
Module 3 update
Dispatch submission
MilestoneDue DateOwnerDependenciesDependency IndicatorsCompleted
Authority acknowledgement expected2025-02-09Sarah ChenNoneIndependentYes
Quality review2025-02-18Nadia PetrovaNoneIndependentNo
Regulatory review2025-03-21James O'BrienNoneIndependentYes
Protocol finalization2025-04-26Nadia PetrovaNoneIndependentYes
QC check2025-05-08Priya SharmaPLAN-034-MS-004DependentNo
Module 5 compilation2025-06-04Lieselotte van der BergNoneIndependentYes
Publishing start2025-07-14Marcus WebbPLAN-034-MS-006DependentYes
Module 3 update2025-08-24Marcus WebbPLAN-034-MS-007DependentYes
Dispatch submission2025-09-22James O'BrienPLAN-034-MS-008DependentNo