This submission plan coordinates owners, milestone dependencies, and readiness controls for Alzaclear. Teams use it to monitor timeline health, resolve blockers, and decide whether content is publish-ready for sequence assembly. Readiness is calculated from deterministic component approval status across linked dossiers, rather than manual estimates. Use the edit and content assembly actions to move directly into corrective work.

Plan ID
PLAN-038
Application
Target Date
2025-04-15
Status
Blocked
Owner
Nadia Petrova
Created
2022-07-16
Readiness Score
10/100
Calculated from 2 approved of 20 linked content components.
Blockers
5 components are missing approval snapshots.
6 components still have unresolved review comments.
Cross-market label harmonisation open
Phase III data reconciliation ongoing
Awaiting CMC stability data lock
Milestone Dependency Strip
Authority acknowledgement expected
CSR draft
QC check
Protocol finalization
Regulatory review
Module 3 update
Publishing start
Module 5 compilation
CSR review
Data cutoff
MilestoneDue DateOwnerDependenciesDependency IndicatorsCompleted
Authority acknowledgement expected2025-01-27Priya SharmaNoneIndependentYes
CSR draft2025-02-19Sarah ChenPLAN-038-MS-001DependentNo
QC check2025-03-10Nadia PetrovaNoneIndependentYes
Protocol finalization2025-03-27Tomoko IkedaNoneIndependentNo
Regulatory review2025-05-14Nadia PetrovaNoneIndependentYes
Module 3 update2025-05-30Tomoko IkedaNoneIndependentNo
Publishing start2025-06-30James O'BrienPLAN-038-MS-006DependentYes
Module 5 compilation2025-07-12James O'BrienNoneIndependentYes
CSR review2025-08-22Nadia PetrovaNoneIndependentYes
Data cutoff2025-09-22Sarah ChenNoneIndependentYes